In this blog, I will demonstrate, step by step, how to add and customize Enterprise Project Structure (EPS) in P6. Enterprise  Project Structure (EPS) enables scheduler to organize and manage all the projects executed by an organization.


The EPS can be subdivided into as many levels or nodes as needed to parallel work in the enterprise. Nodes at the highest, or root, level might represent divisions within your company, project phases, site locations, or other major groupings that meet the needs of your organization, while projects always represent the lowest level of the hierarchy. Every project in the enterprise must be included 
in an EPS node.

To setup EPS in P6, follow the following steps:

1. Open P6



2. In the main menu, go to Enterprise > Enterprise Project Structure


3.  Click Add in the EPS dialogue box


4. Change EPS ID and EPS Name as per your requirements

5. Use Arrows to correct the level of EPS node


6. To change EPS view from Table View to Chart View: Right Click > Chart View


7. Chart View of a new EPS system created using above procedure is shown below. Try making a similar one using above procedure!



I hope the above procedure will help you in making an EPS system for a consultant, contractor or government organization in P6. If you have any question or feedback, jump to comments section.

Stay tuned for more webcasts on P6!